October 8, 2026
In an April KSBY interview, as crews were starting on the Five Cities Project, a resident described the highway as "very congested at certain times of the day," and added, "If you live here, you know when to get onto 101."
Six months on, anyone driving the Price Street corridor or the Spyglass, Mattie, and Wadsworth underpasses has worked out a second timing rule: when the flaggers are out. The project was pitched as three pieces delivered together. Only two of them are now on track to arrive together. Since June, the third piece, the one that would have given Shell Beach a continuous walking and biking route toward Avila, has been on its own timeline, and that timeline has no end date.
SLOCOG, the San Luis Obispo Council of Governments, sponsors the project, and its project page breaks the budget into two lines.
Funding on that same page adds up to $80.3 million: $13.4 million from SLOCOG, $64.9 million from the state's SB 1 Trade Corridors Enhancement Program, and $2 million in 2026 federal Community Project Funding secured by Rep. Salud Carbajal. That leaves the project $7.4 million short of its own cost estimate, and the whole shortfall sits on the path line.
The project's stated purpose ties these pieces together. SLOCOG says southbound 101 runs near peak capacity during commute hours and the summer travel months, and that drivers avoiding the jam reroute onto Shell Beach Road, "which exposes local roads to heavy traffic and increases safety risks for pedestrians and cyclists." The project's answer to that problem has two parts: fewer cut-through cars, and a separated path for the people walking and biking beside them. The first part is funded. The second part is the one that stalled.
SLOCOG still calls the path "underfunded." A Pismo Beach City Council staff report on the Aug. 18, 2026 agenda shows the actual status is weaker than that. The plan had been to pay for the path out of the same roughly $65 million Trade Corridor Enhancement Program award that covers the lane and the park-and-ride lot on Price Street south of Mattie Road. Construction bids changed that.
"However, the construction cost came in higher than expected, leaving a shortfall of funding for the SBSUP. The City and The San Luis Obispo Council of Governments (SLOCOG) worked together to reduce the scope of the Phase 2 project to fit the programmed TCEP construction budget. A scope change request was submitted to the California Transportation Commission (CTC). On June 9, 2026 the City was notified that the CTC did not approve the scope change request, and the TCEP construction funding lapsed."
SLOCOG's draft agenda packet for its Oct. 7 board meeting fills in the dates. Staff were notified of the denial on June 9, and the $3.6 million in TCEP grant funds lapsed on June 30. Those funds do not return to SLOCOG. A separate $3.2 million in SLOCOG regional funds lapsed the same day, though that money can be reprogrammed in the 2028 cycle. Some construction money is still committed. Carbajal's $2 million in federal Community Project Funding is set to be programmed for path construction in the 2027 Federal Transportation Improvement Program. The packet puts current commitments at $5.2 million, $1.55 million below the project budget in the 2026 regional plan because of the lost TCEP funding.
After that, staff changed course. The City divides the path into phases. Phase 1 is the Terrace-to-Cliff segment completed in 2021. Phase 2 runs from Avila Beach Drive to Spyglass Drive. Phase 3 runs from Spyglass Drive to Terrace Avenue. Staff proposed pausing Phase 2, starting preliminary design on Phase 3, and packaging the two as one project for "a future Active Transportation Program (ATP) grant application."
The money involved is small next to the highway budget. Wallace Group, the engineering firm the Council hired on Nov. 19, 2024 for $926,857 to design Phase 2, had $224,119 left on its contract. About $288,967 in Surface Transportation Block Grant funds remained in the Phase 2 design budget, and SLOCOG confirmed those funds could go toward Phase 3 design. The amendment on the Aug. 18 agenda covered survey and right-of-way boundary work on Phase 3 within the existing contract cost. The agenda listed it as a consent item. The materials reviewed for this post don't record the Council's vote.
That pause reverses the City's own map from a year earlier. A concept plan attached to the Sept. 16, 2025 Council agenda showed Phase 2 construction in 2027 and Phase 3 as "TBD." The SLOCOG packet now targets a combined Phase 2 and 3 application in ATP Cycle 9, in 2028, once environmental review, design, and right-of-way clearance are done. It also notes that right-of-way coordination with Caltrans can take up to 18 months in many cases.
Phase 1 is the Shell Beach streetscape most residents know. The City's original project description puts it between Shell Beach Elementary at Terrace Avenue and Dinosaur Caves Park at Cliff Avenue, built as an eight-foot multi-use path for bicycles and pedestrians. In a 2024 KSBY report on the proposed extension, one resident said he walked, ran, or biked along Shell Beach Road every day.
The extension would carry that path north to where Shell Beach Road meets Avila Beach Drive, near the new Highway 101 roundabout and the Bob Jones pathway. The City's visitor guide describes the Bob Jones Trail as a five-mile paved route beside the creek, with its trailhead off Ontario Road. The same guide currently routes cyclists from Pismo to Shell Beach on dedicated bike lanes along Price Street as it becomes Shell Beach Road. Phase 2 would stop at the Avila Beach Drive roundabout. A link from there to the Bob Jones Trail on Ontario Road is the subject of a separate SLOCOG scoping study, which the October packet says is nearly complete but has no identified delivery path yet. For now, the stretch from Terrace Avenue to Avila Beach Drive exists as design work waiting on a grant.
Everything happening on Price Street and at the underpasses serves the funded pieces. Crews started a retaining wall along Price Street on April 6. It will run about 1,200 feet. It makes room for the widened southbound lanes without disturbing the rock formation in the highway median, which SLOCOG identifies as a Chumash cultural site. Starting the week of July 20, heavy metal barriers went up at the Spyglass Drive, Mattie Road, and Wadsworth Avenue bridges for widening work. Lanes are narrowed through the underpasses and on Price Street, and two lanes stay open.
As of SLOCOG's latest posted update, dated Aug. 18 and aimed at families on school runs, construction and flagging can happen at those three underpasses Monday through Friday between 9 a.m. and 3 p.m., with delays of up to 10 minutes. On Price Street, from downtown north to Mattie Road, SLOCOG's notices list traffic control and on-street parking restrictions from 9 a.m. to 5 p.m. on weekdays, with access to businesses, hotels, and homes kept open. Over Labor Day weekend, 953 The Beach carried SLOCOG's warning of slowdowns on that stretch and at the three undercrossings. The overnight closure dates posted in August have all passed. SLOCOG's project page is the place to check for new ones.
Accounts of how far along the work is differ. SLOCOG wrote on Aug. 2 that crews had combined highway Stages 2 and 3 with the Stage 1 work on Price Street to shorten the schedule. On Aug. 13, SLOCOG transportation planner Stephen Hanamaikai told KSBY, "I believe there's five stages, so we're still in stage one prepping for stage three." Both accounts point to the same finish line. Caltrans District 5 lists fall 2028 for completion.
The Pismo Preserve overflow lot is the other cost locals are carrying. It closed to become a construction staging area and will later be the site of the park-and-ride, with the closure expected to last through 2026. In April, Hanamaikai said Preserve parking would open again "beginning probably in January 2027." That was an estimate, not a confirmed date. Our earlier look at how the Pismo Preserve toll changed trail traffic covers the main lot.
The path skipped the Cycle 8 round on purpose. Cycle 8 drew $3 billion in requests, more than $2.6 billion beyond the money available. SLOCOG's project team decided a combined Phase 2 and 3 application would compete better than Phase 2 alone.
The next step to watch is closer than 2028. The City's August staff report said staff expected "additional funding will be available through SLOCOG this fall" and planned to return to the Council with a contract amendment to finish Phase 3 design. The Oct. 7 SLOCOG agenda and a later Council item will show whether design money for the combined project comes through. Meanwhile, San Luis Obispo County Supervisor Dawn Ortiz-Legg has called the current delays "the little bit of pain that we're going through right now," worth it for the region in the long run. As of now, that payoff is a five-hour afternoon lane and a parking lot, and the path along Shell Beach Road has no construction date.
A multi-year road project with one piece funded and one paused can change what a home near Price Street or Shell Beach Road is worth, and when it makes sense to list. If you own along this corridor and want to talk through how the construction schedule fits your plans, Total Real Estate Advisors can go through the timeline with you. Schedule a free consultation.